Horizon: every supplier in the machine

Texas Advanced Computing Center (University of Texas at Austin), United States

Accelerator
NVIDIA Blackwell GPUs on the Grace Blackwell GB200 NVL4 platform, 2 per node, 2,000 GPU nodes (4,000 GPUs); 185 GiB HBM3 listed per GPU
Host CPU
GPU nodes: 1 NVIDIA Grace (72 cores) per node. CPU partition (planned): 4,750 nodes with two 88-core NVIDIA Vera sockets each
Integrator
Dell Technologies (Dell Integrated Rack Scalable Systems with direct-liquid-cooled PowerEdge servers)
Nodes
2,000 Grace Blackwell nodes in 28 racks of 72 nodes (144 GPUs, about 215 kW each); 4,750 Vera nodes planned in 66 racks of 72 dual-socket nodes (over 100 kW each); 128 cabinets in all, including 34 storage, switching and management racks
Memory
GB200 node: Grace CPU with LPDDR5X (120 GiB per CPU in the user guide's text, 240 GiB in its table) plus 2 Blackwell GPUs with 185 GiB HBM3 each. Vera node memory not published
Interconnect
NVIDIA XDR InfiniBand (Quantum-X800): 800 Gb/s per Grace Blackwell node and 400 Gb/s per Vera node, two non-blocking fat trees (2,000 and 4,750 ports) joined by a third level; about 9,000 endpoints and over 15,000 cables
Storage
VAST Data shared all-flash file system, about 400 PB usable for $HOME and $SCRATCH, 8 TB/s write and 16 TB/s read; storage back end designed and provided by VAST
Cooling
Direct-liquid-cooled racks with rear-door cooling, 7 coolant distribution units and PG-25 coolant; hall built for up to 250 kW per cabinet inside Sabey's Round Rock campus
Power
TACC estimates about 13 MW for the 128 cabinets (August 2026 slides); the hall is described as a 20 MW data center (user guide) or 15-20 MW (TACC announcement). No measured figure published
Rmax (HPL)
Not on the TOP500 in any source read. TACC reports native HPL of 124.3 PFlop/s on about 3,700 GPUs and expects about 130 PFlop/s from the full GPU partition (August 2026 slides)
Rpeak
Not a list figure. TACC's quoted FP64 peak has varied: 300 PFlop/s (Dell and TACC, November 2025), 360 PFlop/s (TACC system page), 160 PFlop/s FP64 for the GPU component alone (user guide)
Status
Installation announced 17 November 2025; as of the August 2026 slides all 4,000 GPUs are on the floor (3,856 powered and cooled, 3,072 tested with HPL and healthy) and only early users have access; the user guide (24 July 2026) says Horizon is still limited to internal users; the Vera CPU partition is expected in early 2027. Production start is given as Spring 2026 (TACC announcement) and Fall 2026 (TACC system page)

Unmarked companies come from the operator's own pages (tacc.utexas.edu, docs.tacc.utexas.edu, lccf.tacc.utexas.edu), its executive director's presentation, or the named vendor's own press release or site (dell, sabeydatacenters.com); reported companies come from named trade press whose article body was read in full, not just the headline. No company on this page is marked reported. This is a map of who plays where, not a confirmed bill of materials: TACC's Horizon system page and user guide (updated August 2026), TACC's 17 November 2025 announcement, a TACC presentation dated August 2026, TACC's Ranch page, Dell's November 2025 press release, and Sabey Data Centers' news pages, researched 2026-10-22

This page is the parts-first view. For Horizon's full system record on the sister site Compute Atlas, an open dataset of supercomputer and AI-cluster supply chains, see Horizon on Compute Atlas.

  1. System design and racks (Dell Integrated Rack Scalable Systems with direct-liquid-cooled PowerEdge servers; 128 cabinets, GPU racks of 144 GPUs at about 215 kW)
    Dell (system integrator; IRSS racks and PowerEdge servers carrying the NVIDIA Grace Blackwell and Vera hardware) · what the vendor named Cambridge supplies (listed beside NVIDIA, Dell, VAST and Sabey in TACC's August 2026 slides, with no description), maker of the rack power shelves, busbars and PDUs — not named in any source read
  2. Grace Blackwell compute nodes (GB200 NVL4: 1 Grace CPU and 2 Blackwell GPUs per node; 2,000 nodes, 4,000 GPUs)
    Nvidia (Blackwell GPUs and Grace CPUs on the GB200 NVL4 platform) · maker of the 185 GiB of HBM per GPU and of the LPDDR5X on the Grace side — not named in any source read, foundry for the Blackwell and Grace dies — no source read for this system names it
  3. Vera CPU nodes (4,750 planned, two 88-core Vera sockets each, 72 nodes per rack; due early 2027)
    Nvidia (Vera CPUs) · node memory capacity and DIMM maker — the slides say nodes will carry more memory than first planned, with no figure, final node count — the slides now say 'guessing still in the 4k nodes/8k sockets/700k cores'
  4. InfiniBand fabric (NVIDIA XDR switches in two non-blocking fat trees joined by a third level; Quantum-X800)
    Nvidia (XDR InfiniBand switches (slides name QM3400 and QM3200 models) and Quantum-X800 platform; the storage back-end network is designed and supplied by VAST) · optical transceiver, active optical cable and copper cable vendors for the 15,000-plus cables — not named in any source read
  5. Shared all-flash file system (VAST Data, about 400 PB usable, 28 storage racks; back-end network supplied by VAST)
    VAST Data (file system and storage back-end hardware for $HOME and $SCRATCH) · maker of the flash drives that make up the 400 PB — not named in any source read
  6. Ranch archive, the companion exabyte archive of the same facility (4 PB Dell flash with Versity ScoutFS, 16 PB Dell ECS, two Spectra Logic TFinity tape libraries; in production since September 2025)
    Dell (4 PB flash front end and 16 PB ECS object store), Versity (ScoutFS file system on the flash tier and ScoutAM archive manager), Spectra Logic (two 15-frame TFinity tape libraries for back-end storage) · maker of the LTO-9 and LTO-10 tape drives and cartridges — not named in any source read
  7. Rack and rear-door liquid cooling (direct liquid cooling in the racks, 28 rear doors, 7 coolant distribution units, PG-25 coolant)
    Dell (the 28 rear doors are described in TACC's slides as Dell's first of this kind; part of the IRSS racks) · makers of the cold plates, quick disconnects, the 7 CDUs and the PG-25 coolant — not named in any source read, the temporary rented chillers TACC mentions using to cover parts shortages — supplier not named
  8. Colocation hall and facility (Sabey Data Centers, Round Rock, Texas; hall built to TACC's specification for up to 250 kW per cabinet)
    Sabey (colocation provider; built the hall to TACC's specification at its Austin campus in Round Rock) · makers of the underfloor cooling pipework, chillers and electrical plant in the hall — not named in any source read, [object Object]

TACC names Dell, NVIDIA, VAST Data, Spectra Logic, Versity and Sabey Data Centers as partners, and its executive director's slides also mention a vendor called Cambridge without saying what it supplies. No source read names the maker of the Blackwell GPUs' HBM, the Grace and Vera LPDDR memory, the flash drives that make up the 400 PB file system, the InfiniBand cables and optics, the in-rack and rear-door heat exchangers, the seven coolant distribution units, or the facility's electrical and cooling plant, so none of those get a line. Several headline figures changed between TACC's pages (peak FP64 of 300, 360 or 160 petaflops depending on the page, 15-20 MW or 20 MW, Spring or Fall 2026 production, 4,750 or 4,752 CPU nodes) and the numbers in the specs follow the most recent operator document, with the differences noted. TACC's own slides say the CPU partition will arrive later and smaller than planned, with more memory per node, and put this down to market conditions. Power and cooling outside the cabinet sit in Layer 6 and Layer 7.

Machine-readable: Markdown ·JSON ·every line of every machine (CSV)

Other machines:El Capitan · Frontier · Aurora · JUPITER · Alps · LUMI · Leonardo · Isambard-AI · Venado · Perlmutter · Eagle (Microsoft Azure) · Eos · Fugaku · MareNostrum 5 · Doudna (NERSC-10). See also the AI rack teardowns and thesupercomputer overview.